Pandemic delays govt infra program

The coronavirus pandemic caused delays in the government’s massive infrastructure program rollout, a key official of the program said on Thursday.

“It (pandemic) had a huge impact. We practically lost at least six months for infrastructure.

MANILA TIMES FORUM (From top left) Presidential Adviser on Flagship Programs and Projects and President and Chief Executive Officer of the Bases Conversion and Development Authority Vivencio ‘Vince’ Dizon; PDP Architects CEO Cathy Saldaña; Manila Times President and CEO Dante ‘Klink’ Ang 2nd; and Damosa Land Inc. Vice President Ricardo ‘Cary’ Lagdameo talk about ‘Maximizing and Monetizing: Structures and Spaces’ during the Manila Times online forum on Nov. 26, 2020. SCREENGRAB FROM FACEBOOK LIVE

And when I say infrastructure, I’m not just talking about public infrastructure. Our private sector partners have also lost that amount of time or maybe even more in terms of development,” said Presidential Adviser on Flagship Program and Projects and Bases and Conversion and Development Authority President and CEO Vivencio Dizon.

Dizon was one of the speakers in The Manila Times’ online forum, “Maximizing and Monetizing: Structures and Spaces.”

“In terms of percentage spending for infrastructure maybe we are at least down by maybe 40 percent,” Dizon said.

The government’s infrastructure spending from 2001 to 2010 only amounted to P100.3 billion, equivalent to around 1.6 percent of the country’s gross domestic product (GDP), he said.

It increased to P378.3 billion or 3 percent of GDP in 2011 to 2016 and further climbed to P932 billion (6 percent of GDP) in 2017 to 2019.

“We spent three times the spending in the previous ad-ministrations on a nominal basis and we spent double in terms of percentage of GDP,” Dizon said.

But 2020 changed everything not just for the Philippines but for the entire world.

“We are left with the situation that we will have negative growth of GDP for this year, and unfortunately our infrastructure spending will also take a hit because of the lockdowns we experienced in the second and third quarters,” he said.

More than 100 flagship projects are included in the government’s Build, Build, Build program with a total cost of P4.3 trillion.

Eight projects worth P370 billion in the Infrastructure Flagship Program (IFP), the main component of Build, Build, Build, have been shelved while their feasibility is being reviewed.

Dizon said 13 projects that aim to contribute to the pandemic response were added to the IFP list.

These are the Land Transportation Office Central Command Center; Motor Vehicle Recognition and Enhancement System; National Broadband Program; ICT (Information and Communications Technology) Capacity Development and Management Program; Water District Development Sector Projects; National Irrigation Sector Rehabilitation and Improvement Project; Balog-Balog Multipurpose Project Phase 2; Jalaur River Multipurpose Project; Lower Agno River Irrigation System; Metro Manila Logistics Network; NLEx Harbor Link Extension to Anda Circle; General Santos Airport; and the Virology Science and Technology Institute of the Philippines, which Dizon said would primarily conduct research on infectious diseases.

Dizon said, “Infrastructure and the development of our spaces will be a key factor in getting us out of the slump that the entire world is in.”

Among the completed projects are Harbor Link, extension of the Sangley airport; Luzon bypass in-frastructure of the Broadband project with Facebook; Angat Water Transmission Improvement Project; Laguna Lake Highway; Phase 1A of the New Clark City; Cagayan de Oro port; Pozorrubio and Rosario exit of the Tarlac; Pangasinan, La Union Expressway; and the new passenger terminal building of the Clark International Airport.

Nearing completion are the Metro Manila Skyway Stage 3, MRT 7, BGC to Ortigas link bridge, and Phase 1 of the Central Luzon Link Expressway.

Dizon acknowledged that “the six years of a presidency will not be enough to finish all the projects.”

“Our biggest problem in past decades has been continuity. When we put projects together, we are not saying that we are going to finish all, we’ve never said that because that is not possible. It’s going to take multiple administrations to finish and continuity is going to be the key,” he said.

“What we are putting together is a list of projects that we believe we can push so that the next person, president, administration can take this over and continue it and finish it,” he added.

For Dizon, the long-term commitment of multiple administrations is needed to get all these projects done.

“Maybe in 12 to 18 years you are going to see the Philippines really transform into a country that we’ve seen the likes of Thailand, Malaysia, Singapore, Taiwan and China have transformed in just a few decades,” he said.


Source: ManilaTimes

Mga Komento

Mga sikat na post sa blog na ito

Leonen is backlog topnotcher

Supreme Court Associate Justice Marvic Mario Victor Leonen has racked up the top spots in his division and the court en banc in terms of pending cases. Marvic Leonen Documents from the court show that aside from 82 unresolved en banc cases, Leonen also has 899 pending cases in the Third Division as of March 31, 2020. The division’s Statistics on Judicial Pending Cases was signed by Division Clerk of Court Misael Domingo Battung erd. Leonen has 199 cases classified as “aging” and 700 “non-aging” cases in the Third Division which he heads. Non-aging cases are cases which are waiting for other pleadings to be submitted. Other members of the Third Division at that time when the statistics were made were Justices Alexander Gesmundo, Rosmari Carandang, Rodil Zalameda and Samuel Gaerlan. Leonen has been with the Supreme Court for eight years, having been appointed by President Benigno Aquino 3rd on Nov. 21, 2012. He turns 58 years old on December 29. He is the division’s m...

TikTok donates $300,000 for typhoon victims in PH

Over the course of two weeks, two devastating back to back typhoons hit the Philippines. On November 1st, Super Typhoon Rolly (Goni) the strongest typhoon ever recorded in recent history struck the southern region of the Philippines. An estimated two million Filipinos have been affected, many of whom lost their homes and livelihoods. Ten days later, Typhoon Ulysses (Vamco) swept through many of the same provinces previously devastated by Typhoon Rolly, including Metro Manila and parts of Central Luzon leaving widespread flooding and power outages. Many areas are still struggling to recover from the aftermath of these calamities. Homes and livelihood across various provinces were lost to floods, strong winds and rain. LGUs and other organizations continue to mobilize and provide assistance to all who were affected by these typhoons, but many are still in desperate need of help. In line with its mission to inspire creativity and bring joy, TikTok has pledged to donate $300,000 (approxi...

NHL exec Colin Campbell explains league’s schedule goals in Canada

NHL senior executive vice president Colin Campbell says the league would like to try to preserve as many full-capacity home games as possible for Canadian fans, but acknowledges other factors are at play in redoing the schedule during the current COVID-19 surge. “You’d like to give the fans the opportunity to go to as many games as they can. They’ve already been shortchanged in the last year and a half … shortchanged completely watching hockey here in Canada,” Campbell said in an interview on the Real Kyper and Bourne show on Sportsnet 590 The Fan on Friday. “It’s a rite of passage to watch the world juniors this time of year for all young kids. I remember growing up watching it. Now, it’s cancelled. We’re trying to save as much as we can and delay it.” The NHL postponed nine more games on Friday because of arena capacity issues in Canada — with teams being allowed anywhere from zero fans (Montreal Canadiens) to 50 per cent capacity (Calgary Flames, Edmonton Oilers, Vancouver Can...